| Developing Construction Cost Estimates
Accurate estimation of the construction cost of a project is extremely important. One
of the most unpleasant bits of news you may ever have to deliver to a client is that the
cost of a project will be more than you had estimated. Construction cost estimating
usually proceeds in one of two ways, either the client provides the designer with a
maximum budget figure, the limit for construction costs , or there is a preliminary period
of study (under the schematic design phase) in which possible schemes are developed and
their respective costs estimated.
If the actual cost of a project is high, one third to one half higher than you had
anticipated, the client may `kill' the project. The designer won't be reimbursed for the
entire fee (either in retail or in fee for service) until the project is complete. If
construction cost substantially exceed the estimate, you can probably kiss the remainder
of your fee goodbye. The client can also sue you. The legal costs, or cost of settling out
of court, will be substantial. As the icing on the cake, if you are aiming at a particular
target market, and you `screw-up' badly on an important project, your client may damage
your reputation in that market, making it more difficult for you to obtain new projects.
Should the project turn out to be only somewhat higher than you had anticipated, twenty
to twenty-five percent higher, the client may not kill the project but may ask you to
re-design the project for no additional fee. If the project is large and you have already
used up your fee in completing the porject, you may be spending tens of thousands of
dollars (or more) redesigning and redrawing the project to bring it under budget. You not
only lose the money required to pay employees to redesign th e project, but also the money
you would have earned working on additional projects.
Understanding the Construction Process
To estimate the costs of construction, you must be familiar with how the construction
process works and how interior design is related to that process. Clear, concise
instructions to contractors and sub-contractors in the form of Construction drawings and
specifications, i.e. construction documents. A good set of construction documents may even
lower the cost of a project. Clear concise documents will allow the contractor to more
accurately bid the project, and reduce his concern for including a hefty contingency cost.
Contractors will bid high on a project to cover any uncertainties or unknowns, areas where
the documentation wasn't clear.
The Construction Specifiers Institute, or CSI, has developed a format for all elements
and types of construction. This format includes sixteen "divisions" which are
numbered according to the sequence in which they normally occur in the construction
process.
General Conditions, which includes the "start-up" concerns such as how much
space they will need at the site for administrative and equipment storage, and schedule,
etc.
Site Construction involves adjustments to the surrounding landscape, or any excavations
for a foundation
Concrete Work concerns the pouring of foundation footings.
Masonry
Metals
Wood
Masonry
Doors and Windows,
Finishes includes non-structural partition wall systems, wall finishes, floor finishes,
acoustical ceilings, etc.
Specialties
Equipment
Furnishings includes all kinds of furniture and systems
furniture
Electrical includes lighting fixtures
Knowing as much as you can about the construction process
will enable you to develop accurate and complete construction documents. It will also help
you understand what conditions may increase the cost of construction.
Factors Affecting Construction Cost Estimating
Some factors can individually affect construction cost estimating include the project:
Size: the smaller the project in terms of scope or
the number of square feet, the more it will cost per square foot. Contractors have a set
of basic start-up costs. These start up costs remain about the same in real
dollars for every project. Thus for a very large and expensiove project, the start
up costs will be a small percentage of the total construction cost. For a small project,
since start-up costs remain stable, they will constitute a large percentage of the total
construction budget. If the cost of start up for any project is $4,500.00, and the total
cost of the project is $450,000.00, the total start-up costs are 1%. However, if the total
project cost is $30,000.00 then the start-up is 15% of the total cost. Start-up becomes a
major cost factor when estimating construction costs for small to medium sized projects.
Type: the type of project or the kind of space you are designing has an impact
on estimating construction costs. The cost of construction depends on the time the
contractors will need to execute the work, the degree of specialization of the work to be
done, and the cost of the materials. Different types of project have different levels of
complexity and detail. A school cafeteria wouldn't require the same amount of time, nor
the same level of complexity, as a four star restaurant. Construction costs for the four
star restaurant would be much higher than the cafeteria even though it probably would have
smaller square footage. Clients may have difficulty understanding variations in costs.
There are three variables in any project, and only two of these can be controlled at any
one time. These variables are:
· the level of quality will
· the size of the
building or space in terms of the total square footage
· the total cost of the
project.
If a client wants a high degree of quality, the cost must be allowed to flex. If the
client has a rigid budget, and a minimum quantity of square footage, then they must
compromise on quality. In this instance cost and quantity are controlled, and quality must
be allowed to vary. You must help the client decide whether quality, size, or cost is the
their biggest priority and explain what the 'trade offs' are in terms of the other
variables.
Special Construction: complexity can greatly increase the cost of the project.
These conditions may include renovations, heavy loading, i.e. large quantities of files or
a library, hazardous materials, etc. Renovation, especially if it requires altering or
moving structural components, can be costly because it necessitates demolition as well as
building. Quantities of files and books are heavy so the flooring may require additional
structural support. Special construction may also be necessary to shield surrounding
spaces from noise, fire and other hazards.
Project accessibility: sites may be difficult to access, either geographically
or because the space is used during business hours, requiring that the project be
scheduled for off hours. This can be a problem when adjacent spaces have sensitive
equipment, or when construction materials containing hazardous chemicals are used in the
construction process. (You will be surprised how many construction materials do in fact
contain hazardous chemicals. This presents a unique problem which has yet to be adequately
addressed, because even if the area under renovation can be physically isolated from other
areas of the building, very often the HVAC system has not been readjusted, and these
chemicals are often circulated throughout the area or building, creating hazards for
occupants. This situation is especially critical in permanently enclosed office buildings
(those whose windows are non-operating, i.e. they don't open) since chemicals can linger
for long periods of time. The most frequent culprits in terms of hazardous chemicals are
glues, paint removers, mastics, carpet backings, and synthetically produced building
materials. Be alert for these chemicals: toulene, xylene, formaldehyde, mineral spirits,
naphtha, and other kinds of organic solvents. In summary, these factors can increase the
time and effort needed by the contractor and result in an increased cost of construction:
· isolating areas under
renovation
· providing physical access to
move materials, equipment, and construction personnel to the site
· ensuring periods of work when
construction will not disrupt the on-going operation of the company
Project clarity: occasionally
there may be a situation where the designer can't provide
complete and accurate information to contractors. These conditions frequently occur when
projects are located in old buildings for which there are no drawings or specifications
documenting the existing structure and conditions. In these situations it is impossible to
know absolutely what is inside of walls (without conducting X-ray investigations, which
are occasionally done under extreme conditions), or other building components involved in
the renovation. Uncertainty of conditions should give both the construction estimator and
the contractor pause. Unknown conditions can increase both the risk and the complexity of
construction, and some allowance must be made in the costs estimates, particularly if
problems are suspected.
Project Difficulty: other factors can also raise costs:
· The project schedule
may be tight, e.g. the client's current lease is expiring and the work must be completed
by a specified date so that the client can move in to their new space. Sub-contractors may
have to work over time or neglect other projects in order to finish work on time. This
will raise the contractors price for the work because many people will need to devote more
hours in a short period of time to the work, increasing the stress on workers, removing
them from other projects on which the contractor is working, making coordination of trades
more difficult, and finally presenting the possibility of needing to pay 'time and a half'
to union laborers (which most construction trades are in many states).
· Level of detail
may also make the project more difficult and costly. Costs will escalate if there are many
components to the work and if components must occur in very tight order or concomitantly,
requiring the general contractor to closely coordinate the building trades on the job.
Client difficulty: if the client has been difficult during the design process,
these difficulties will affect the construction process. A demanding client who may anger
construction crews, an indecisive client who may wish to make changes up to the last
minute or later will obviously raise costs. The client's problematic behavior is difficult
to explain, let alone bill. It may be wise in these cases to incorporate a larger than
normal contingency into your cost estimates allowing these difficulties to be accommodated
without having to point out to the client that they themselves are the problem.
Contractor problems: a client wants to work with a particular contractor. You
know that sometimes this contractor may underbid the project, i.e. they quote a price for
the work, which is not adequate for them to actually complete the job. They submit a lower
bid than competitors to secure the project. After the contractor low balls the bid, they
slowly raise their costs throughout the project by claiming that particular items or
services were not included in their original package. Clients will occasionally blame
designers in this situation rather than the contractors. To protect yourself, when the
client accepts an unreasonably low bid, put it in writing that, according to your
estimates, the project should cost substantially more than the contractor has quoted.
Contractors also may argue that problems in the process caused delays and that they are
entitled to additional fees. However, you can avert this situation by having very clear
and accurate drawings and specifications that leave no room for uncertainty. Estimating
the cost of these problems is almost impossible, so you should do everything in your power
to dissuade the client from employing a a contractor who is known to be difficult or
unreliable despite a previous relationship with the client or a low bid.
Time of Year: building construction is a seasonal enterprise. There are periods
of the year when contractors are busy and can barely keep up and then there are periods of
the year when they are likely to be looking for work. From early January to late February
or early March, General Contractors will be seeking work to fill their schedule for the
following construction season (approximately early April through late October or early
November). During this time you are more likely to get a more competitive bid for a
project. After this period it is likely that bids will be higher or the contractors who
are available will be the less qualified and were not hired for other projects.
Competition: the competition among contractors in the area where the project is
being constructed will also affect the cost of the project. Factors affecting competition
include
· the number of qualified
contractors operating in the project area. The more qualified contractors, the greater the
potential for competitive pricing and the lower the construction cost. The key here is in
the phrase "qualified contractors," contractors who can successfully complete
the project. Many contractors and sub-contractors are suspect. The easiest way to
determine whether a contractor is qualified is through their bid. If it is much lower
than their competitors', there is probably good reason. You should be suspicious if any
bid is out of line with the others, either very low or very high. If you obtain five bids
for a project: $180,000, $93,000, $83,000, $73,000 and $45,000, you can be relatively sure
that the extreme numbers indicates some sort of problem. If the project is awarded to the
low bidder, you may have real problems getting a quality project built. In most government
projects you may be required to accept the low bid. It is very important to develop
very tight drawings and specification to ensure that those who are bidding on a project
are forced to complete the project according to your design.
· to obtain a
competitive bid, you must allow bidders some discretion in their pricing of the project.
Your drawings and specifications must be specific enough to convey to the contractor the
level of quality you expect, but still leave them enough choice to provide opportunities
for them to select approaches, materials and personnel which are perhaps less expensive
than those which their competitors will choose. In your text (Piotrowski, Chapter 23, pp.
321 - 329) the author speaks of several types of specifications "Closed and Open
Specifications." (Please be sure to read these sections careful along with this
lecture).These categories of specification are very important because they can
determine the degree of competition possible in pricing a project. A closed specification
eliminates most competition, but ensures that every aspect of the project will be
constructed or installed as it was designed. If the project is to be high quality, a
closed specification is the most appropriate approach to construction documentation.
However, if a somewhat lesser level of quality is acceptable, a more open format for your
specifications is appropriate. The openness of the specification will allow greater
competition in pricing and allow you to produce a cost estimate which is closer to the
norm in terms of similar types of projects.
. Labor Rates: the general state of the economy will affect the cost of a
project so it is important to watch what is happening with the rate of inflation in
developing accurate construction estimates. When the economy is booming (like it is now)
and the unemployment rate is very low, there may be some wage pressure, particularly in
the skilled and labor intensive construction industry. If there are indications of
inflationary pressures, you must place some limits on your construction estimate. You
should either indicate to the client that the period for which such an estimate is
accurate will be relatively brief, or include some budgetary contingency for inflation
over the period before bids are 'let' and the project is awarded to a contractor.
. Material Costs: the type and availability of a particular material can also
affect your approach to a cost estimate. If your client insists upon a particular material
or if a particular manufacturer's product is crucial to the success of a project, the cost
of that specific item can drive up the cost of the project. This is essentially a closed
specification. If, however you can accept a material of equal or somewhat reduced quality,
you will leave room for greater price competition and lower the project cost.
(Incidentally, the availability of a product or material can also affect the success of a
project relative to the client schedule expectations. When you are selecting products or
materials, you should also consider the concerns of "lead time" (the time it
will take for an order to be manufactured and delivered).
General Economic Pressures: the general state of the economy must be considered
in developing a cost estimate for your project. Inflation affects not only labor but also
materials and the cost of the money the client may need to borrow to complete a project.
If you think that there will be an extended period between the time when you develop your
cost estimate and the actual time when the project goes out to bid, then you will need to
account for inflation in your cost estimate, adding a reasonable percentage to the total
cost.
Estimating a construction budget
There are three primary variables in developing an estimate of construction cost, only
two of which can be controlled at any one time.
size of the project: the larger the project, the greater economy of scale
that the contractor is able to achieve and thus the lower the unit costs of all of the
components of the building.
quality and level of detail, difficulty, as mentioned
above, will affect the cost per square foot
total project cost
You must convey that only two of these variable can be controlled,
not all three. You must either establish the amount of space which your client needs, or
the quality of the design, detailing, finishes, and materials, e.g. lighting or
furnishings, in relation to the budget client's budget.
The designer must have some idea about the position of these three variables. Establish
the priority of these variables with the client to ensure a simplified design process as
well as the client's satisfaction. Two ways to approach this include:
the client establishes a maximum construction cost for the project and the designer
then keeps the design within these budgetary constraints. This approach provides the
designer and client with some certainty regarding the ultimate cost of the project. The
designer should assist the client in establishing a clear and reasonable budget for the
project budget before any drawings are developed. The client may share with you the amount
of money they are willing to spend, but it may be difficult to get the other two
variables, project size and project quality, related to the cost in a manner which will
suit the client. Most clients have a poor understanding of the amount of space which will
best serve their needs. Most underestimate and some may over-estimate. It also can be
difficult to establish the level of quality the client expects. The task of aiding the
client in determining a budget figure in relation to levels of quality and quantities of
space is easier if you, or your firm, have experience in the same type of project. You
then can provide the client with photographs and plans of similar projects to give them an
idea about the amount of space they might need and the levels of quality available for a
certain price range. By attaching a per square foot cost to these completed projects, you
can give the client a reasonable idea about what they can get for the amount of money they
are willing to spend. The advantage of this approach is that you have some idea of the
time and effort which you'll need to complete the project and you also have some idea what
the client expects. The disadvantage to this is that you don't have the opportunity to
explore new possibilities and potentially better solutions. You may be limited in your
creative efforts so that the project to be less personally satisfying. This first approach
to cost estimation is best used when cost is the primary concern. It focuses your efforts
on controlling cost as the primary variable. You may also establish with your client
through the examination of floor plans and photographs the second variable, either the
size of the project or the level of client's preferrd level quality. If you and/or your
firm do not have experience in the type of project, it is safer to use the second approach
to cost estimation.
An alternative method is for the designer to develop
several options for a cost range and then estimate the construction costs based on several
standard estimating approaches. This process is less efficient in terms of your efforts as
a designer because it requires a broader investigation. However, the process of developing
several schemes provides greater opportunity for innovations which may be more cost
effective and creative. In this approach, the designer develops the program and several
schematic options at various levels of cost, size, and quality. This is like creating an
option which is a Hyundai, one which is a Buick, and one which is a Rolls Royce. When you
present these options to the client you can encourage them to choose a higher level of
quality since they are able to see the advantages in committing more of their financial
resources. The client has more opportunity to choose among the variables of cost, size and
quality. In this approach the client may be as interested in the less tangible concerns of
size and quality, as opposed to cost. It is still important to make it clear to your
client that only two of the three variables can be controlled, and that if
the amount of space, and the quality of the environment are of paramount concern, the
client must be willing and able to bear the cost. In either of these approaches, the
designer is bound by the cleint's priorities. If cost is the primary concern, the designer
must respect that decision and contain costs. If quality is the most significant issue,
then the designer provide the level of quality desired, while at the same time aiding the
client in determining whether the size of the space or the cost will be the second
priority.
To determine the cost of any single option in this approach the designer can use one or
more construction cost databases. The best known of these databases is published yearly by
the R. S. Mean Company. The database, commonly known as the Means Index, provides
average cost data in various formats. Each cost format is in a single volume (or on CD)
addressing a particular method or approach to estimation. The four approaches which you
know are
R S Means, Repairs and Remodeling Costs
R S Means, Square Foot Costs, which provides an
average cost per square foot for various types of projects such as hospitals and schools
R S Means, Building Construction Cost Data, which
provides the cost of new construction
R S Means, Interior Cost Data
Cost estimating databases have a basic format, but can be arranged in a number of ways:
· aspects of
construction are arranged in the CSI format. Under each CSI Division, the technical
section is noted and a brief description is given of the item or system for which a cost
figure is being provided.
· a description of labor
follows with the average amount of what work can be done in a single day.
· the type of unit in
which the cost is given, for instance the cost per square yard of carpeting, or the cost
per linear foot of a ten feet tall gypsum board partition.
· the "bare
costs" are given. These comprise parts of an overall cost per unit, broken down into
· the cost of the material
required
· the cost of the the labor
required
· the cost of the equipment
required.
· these three costs are
then totaled
· a cost which includes
the contractors overhead and profit for the unit.
· By going through all
of the elements of the project, a designer can develop a good estimate of the cost of
construction. Be sure to double check your estimates.
· if the project is very
large or very important, you can hire a professional estimator. This approach will cost
money, but it will provide you and your client with greater assurance that the project
will be within budget.
· you can check your
estimate with another kind of estimating database. For instance, through totaling all of
the individual costs for various elements of the project, and then dividing by the total
square footage, you arrive at a figure of $56.00 per square foot for constructing a 15,000
square foot tenant office. You might then look at the cost per square foot reference and
find that the average cost per square foot for such work is only $48.00 per square foot.
Did you do something wrong? You must look carefully at what level of quality and size are
provided as a reference. If the reference is for 120,000 square feet, the economy of scale
in larger project would lower the cost. Or, if the reference calls for VCT on the floor
and, painted gypsum board partition walls, and your project has carpeted floors and vinyl
wall-covering, than you could expect a higher cost than the reference. If the size and
quality of the reference are similar to your estimate, then your estimate is probably
close to reality.
· if you feel you can
trust a local contractor or if you are dealing primarily with items whose costs can easily
be determined, you can telephone and the dealer and ask for an estimate. If you assure
them that they can bid on the project, they may give you their opinion or a price quote.
CYA:
If you are going to provide your own cost estimate, you need to be accurate. Even
clients who are not very concerned about cost are disturbed when a cost estimate is much
lower than the actual cost of the project. It is difficult to undertake a project and not
be able to provide the client with some idea of how much it will cost, but it is better to
say you don't know, and do what you can to find out, than to give a figure which is
inaccurate. Remember, if a client remembers nothing else during the course of a project, they
will remember the estimated cost you offered, even if you only offered a verbal guestimate
in a moment of weakness. To protect yourself:
Impress upon the client that what you have produced is
only an estimate. You should provide a statement of this clearly on any written
documentation of your estimate.
Include in your estimate a "contingency" amount, i.e. a percentage, usually
between fifteen (15 %) and twenty (20%) which you add to your total estimate. By including
a contingency you can protect yourself to a certain degree by having a final number much
higher that the actual cost, so that even if the total cost is substantially higher
than the actual cost you are reasonably safe.
The estimate should present a worst case scenario. When
preparing a cost estimate, you should try to include every possible cost you can think of
including fees which the state may charge to approve the construction drawings, fees for
removal of asbestos, and any additional fees which you may require in order to complete
the project.
Looking For Construction
Loans?
|